Please check below for updates on the Cookham Bridge refurbishment work.
Tuesday 7 May 2024
Since the previous update
Final works underneath the bridge have been continuing and the following activities are now complete:
- Bearing pad cages complete on all 4 corners
- New bearings installation completed
- Concrete pads poured and completed
- Grout beds round the bearings completed
- Bridge 100% de-jacked
- Painting the underside of the deck at each abutment complete
- Brick facade reinstated on the north
Remaining activities
- Remaining brick façade to reinstate
- Bearing shelf to reinstate
- Drainage to reinstate
- Strike scaffold
- Site clear to complete and de-mobilisation