Information on a number of licensing applications for example, skip, road traffic signals, erecting a banner, crane licence and much more.
The road closure application form should be used to apply for a road closure or public right of way closure to facilitate works or events on the highway or public right of way (PROW).
The applicant will be contacted after the submission of the application to confirm whether the closure times and dates can be accommodated and whether the documents submitted are considered as sufficient and of the required standard.
The closure would allow for the road/PROW to be closed between set points or for its full length, however it would not stop vehicles from being able to legally park in the said road. If you require for the area to be cleared of vehicles as well as being closed a Parking Suspension might be required.
We would not consider close of a road/PROW for extensive duration, where the road is traffic sensitive or where it is believed that the proposed event is not safe or would cause major disruption to Highway Network.
In all the cases we will contact the applicant and advise of issues with the application and submitted proposals.
Please note: For new events where a road closure will be required a meeting with Network Management will have to be arranged no later than 10 months prior to the proposed event date to discuss proposals and traffic management and any potential impact on residents and road network. In addition a submission to Safety Advisory Group will have to be made.
In order to make an application you have to fulfil the following requirements:
When completing the application clear information needs to be provided in relation to the extent of the closure, closure times and reason why the closure is required. Statements “As per attached drawing” or “Not sufficient width”, “From House X 50 metres” will not be accepted and the application will be considered as incomplete.
Applications will be considered as incomplete if the required documents and CAD drawings are not provided and will not be processed.
Apply for: Road or public rights of way closure