| Surface Water Drainage Strategy/Surface Water Drainage Layout |
This should include; existing drainage arrangements with detail of how the site currently drains and a topographical survey, a surface water drainage layout with the location of drainage components, pipe gradients/numbers/diameters, storage volumes, outfall location, exceedance flow routes, proposed impermeable areas, infiltration areas, attenuation devices, design levels that function hydraulically, topographical survey detail and a method of surface water disposal in line with the SuDS Management Hierarchy. |
Pre-App
Outline
Full
|
| Flood Risk Assessment |
This should include; surface water, groundwater, fluvial, reservoir, sewer and any artificial waterbodies, consideration of how flood risk may change in the future such as climate change, application of Sequential Test and Exception test if criteria met, demonstration of a sequential approach to locating a development and consideration of mitigation measures. |
Pre-App
Outline
Full
|
| Outline Calculations |
This should include; Greenfield, Brownfield (if applicable) and post-development runoff rates, volumes of attenuation required. |
Outline |
| Full Calculations |
Surface Water drainage modelling calculations (e.g. MicroDrainage) which show the attenuation volumes provided on site for the 1 in 30 year and 1 in 100 year + Climate Change events. |
Full
Reserved Matters
Discharge of Conditions
|
| Groundwater Investigation (Infiltration only) |
This should include; evidence of ground conditions, groundwater levels and site- specific infiltration tests in line with BRE 365 regulations. |
Outline
Full
Reserved Matters
Discharge of Conditions
|
| Water Quality Assessment |
This should be completed using the Simple Index approach as detailed in the CIRIA SuDS Manual (C753). |
Full |
| Flood Exceedance Plan |
Plan indicating where surface water would flow in exceedance events. If flooding is modelled to occur on site during 1 in 30 or 1 in 100yr + Climate Change, the estimated volumes and depths should be included on the plan. |
Full
Reserved Matters
Discharge of Conditions
|
| Maintenance Plan |
Full Description of required maintenance activities or each drainage element and who is responsible for carrying this out. The site layout should include access routes and space for maintenance activities to commence. |
Full
Discharge of Condition
|
| Development and Construction Plan |
Details of surface water management plans through construction. This should include details of flow routes and how these will be manged and maintained during development. |
Full
Reserved Matters
Discharge of Conditions
|
|
Discharge Agreements
(temporary and permanent)
|
Confirmation that any required discharge agreements with third parties are in place. |
Full
Reserved Matters
Discharge of Conditions
|
|
Evidence of third party agreements if required.
|
Proof that any proposed modifications to watercourses and/or connections to third party infrastructure receiving water are viable and acceptable. This can be agreement in principle. |
Outline
Full
|