PHASE 1 (Enabling works)

Works completed April 2020.

PHASE 2 (Main works)

Works commence on Monday 17 August 2020 for a duration of 21 weeks until Friday 8 January 2021. The main structure repairs will be carried out during this time.

Dates and lane closures

Monday 17 August to Wednesday 19 August 2020

Northbound and Southbound Full closure 10pm to 6am. The road will be closed to all traffic in both directions.

Monday 17 August to Thursday 12 November 2020

Northbound and southbound permanent lane closures - on both north and southbound carriageways.

Wednesday 26 to Friday 28 August 2020

Northbound Full closure (from Clarence Road to junction 6 M4) 10pm to 6am. The road will be closed to all traffic in the Northbound direction.

Thursday 3 to Saturday 5 September 2020

Northbound and Southbound Full closure 10pm to 6am. The road will be closed to all traffic in both directions.

Thursday 17 to Saturday 19 September 2020

Northbound Full closure (from Clarence Road to junction 6 M4) 10pm to 6am. The road will be closed to all traffic in the Northbound direction.

Thursday 24 to Saturday 26 September 2020

Northbound and Southbound Full closure 10pm to 6am. The road will be closed to all traffic in both directions.

Thursday 8 to Saturday 10 October 2020

Northbound Full closure (from Clarence Road to junction 6 M4) 10pm to 6am. The road will be closed to all traffic in the Northbound direction.

Thursday 15 to Saturday 17 October 2020

Northbound and Southbound Full closure 10pm to 6am. The road will be closed to all traffic in both directions.

Tuesday 3 to Thursday 5 November 2020

Northbound Full closure (from Clarence Road to junction 6 M4) 10pm to 6am. The road will be closed to all traffic in the Northbound direction.

Tuesday 10 to Thursday 12 November 2020

Northbound and Southbound Full closure 10pm to 6am. The road will be closed to all traffic in both directions.

Friday 27 to Sunday 29 November 2020

Northbound Full closure (from Clarence Road to junction 6 M4) 10pm to 6am. The road will be closed to all traffic in the Northbound direction.

Friday 4 to Sunday 6 December 2020

Northbound and Southbound Full closure 10pm to 6am. The road will be closed to all traffic in both directions.

Thursday 10 to Sunday 13 December 2020

Northbound and Southbound Full closure 10pm to 6am. The road will be closed to all traffic in both directions.

Tuesday 5 to Thursday 7 January 2021

Northbound and Southbound Full closure 10pm to 6am. The road will be closed to all traffic in both directions.

Highways team : Contact details

For further information, please contact us by:

Highways Team - Royal Borough of Windsor and Maidenhead
Town Hall, St Ives Road,
Maidenhead SL6 1RF
Telephone: 01628 683800