| Road | Treatment* | Working Restrictions | Provisional Site Start Dates** |
| High Street (B378) - Winter Road to Station Road | SD | 0930-1630 hrs | Complete*** |
| Montagu Road - full length | MA | - |
1st-2nd December 2008 |
| Southlea Road (B3021) - full length (parts) | SD Remedials | 0930-1630 hrs | Complete*** |
| Staines Road (B376) - Magna Carta Lane South to 30/40mph limit | SMA | Road Closure | Deferred due to utility works - to be reprogrammed in Autumn / Winter 2008 |
| Stanwell Road - Datchet Road to Coppermill Road | SMA | Road Closure | Deferred due to utility works - to be reprogrammed in Autumn / Winter 2008 |
| The Green - full length | SD | - | Complete*** |
| Welley Road (B376) - over railway bridge between Stop lines | SMA | Road Closure 0900-1600 hrs, road will be open outside these times | Complete*** |
* Please see Resurfacing FAQs for explanation of the different surface treatment types.
** Programme dates are provisional, and are dependant upon favourable weather conditions.
*** Surfacing works are all complete, however some lining and remedial works may still be outstanding on some sites.