Road Treatment* Working Restrictions Provisional Site Start Dates**
Bottle Lane, Knowl Hill - railway bridge to A4 Patching Closure Complete ***
Broadmoor Road, White Waltham - Smewins Lane to Walgrove Gardens SMA Closure Complete ***
High Street, Cookham - full length SMA - 22-26th March
Long Lane, Cookham Dean - Spring Lane to Cannondown Road Patching Closure 30th March
The Pound, Cookham - along The Causeway Patching 0930-01630 hrs 31st March - 6th April
Waltham Road, White Waltham - Church Hill to Innings Lane SMA Closure Complete ***
Warren Row Road, Knowl Hill - A4 to Pudding Hill Patching - 30th March

* Please see Resurfacing FAQs for explanation of the different surface treatment types.

** Programme dates are provisional, and are dependant upon favourable weather conditions. Dates are as per programme update issued 18th March.

*** Surfacing works are all complete, however some lining and remedial works may still be outstanding on some sites.


How do you rate this information/service?
Help - What does this mean?
Find us on:  Follow RBWM on Twitter RBWM YouTube video channel
Modified: 2010-03-19
Author: Phillip Milward
Editor: Carol.Cornell
LGSL PID:
RDCMS ID: 20110